PEOPLE PLUS - ASTON
Out of gallery
KEY FACTS
-
Major dilapidations of 30,000ft2 facility back to open plan warehouse/offices.
-
Completed in 10 weeks
-
Resulted in early release and return to landlord
SCOPE OF WORKS
We assisted People Plus in the managed retreat from a 30,000ft2 training facility in Birmingham - resulting in an early release and return to the landlord
The works were completed on time in 10 weeks and on budget
Both the landlord ( a multi billion portfolio holder) and their agents, TFT the national dilapidations specialist surveying group, were very impressed by our performance and have returned to use us again and again.